MAINTAINING TRAFFIC

While the improvements are being constructed along East 105th Street, northbound and southbound traffic will be maintained at all times.  The contractor will build one side of the road, while providing travel lanes on the other side of the road.  Once the first side is complete, the contractor will flip to the opposite side.  Access to all properties and side streets will be maintained at all times.  Construction will happen in two phases described and shown below. 

SEWER PREWORK

Prior to the start of the surface roadway improvements, the City is going to repairs a section of underground sewer from Helena Avenue to the I-90 overpass.  To make these improvements the contractor will be working in the center of the street while maintaining northbound and southbound traffic along the outside of the street (along the curbs). As seen in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by an orange barrel.  Access to all properties and side streets will be maintained at all times. 

PHASE 1 - MAINTENANCE OF TRAFFIC

During Phase 1 of construction the contractor will build the west side of the road while maintaining northbound and southbound traffic on the east side of the road.  As seen in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by an orange barrel.  Access to all properties and side streets will be maintained at all times. 

PHASE 2 - MAINTENANCE OF TRAFFIC

During Phase 2 of construction the contractor will build the east side of the road while maintaining northbound and southbound traffic on the west side of the road.  As seen in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by an orange barrel.  Access to all properties and side streets will be maintained at all times.